Building a 4-bedroom house in Yemen typically costs $80,640 to $149,760 in construction cost — roughly $336–$624 per square metre over 240 m² of floor area. That excludes land, professional fees and statutory charges.

Yemen is one of the lower-cost construction markets in the world — it ranks 192 of 200 countries on our construction cost index, at about 24% of United States build costs. This page prices a 4-bedroom house — large single-storey family home, four bedrooms, en-suite master, double garage allowance — at 240 m² of gross floor area, then breaks the cost down element by element so you can see where the money actually goes. Costs are quoted in USD for comparability; the local currency in Yemen is YER (﷼), and a bill of quantities generated from your own drawings is priced in YER using the POMI standard.

Advertisement
Total construction cost
$80,640 – $149,760
Cost per m²
$336 – $624
Gross floor area
240 m² · 1 storey

What is being priced

The figures on this page price a 4-bedroom house in Yemen at 240 m² of gross floor area over 1 storey, specified as large single-storey family home, four bedrooms, en-suite master, double garage allowance. Construction cost only — land, professional fees, statutory charges, utility connections and loose furniture are all excluded, and together commonly add another 15–30%.

Cost by specification level

SpecificationConstruction cost (USD)
Basic / low-cost finish$58,061$107,827
Standard finish$80,640$149,760
Premium finish$116,928$217,152
Advertisement

Where the money goes

Elemental split of construction cost for a 4-bedroom house of this type. Percentages are concept-stage cost-planning proportions; the ranges below apply them to the totals above.

ElementShareCost (USD)
Substructure & foundations
Excavation, strip footings, hardcore, blinding, DPC and ground slab.
15%$12,096$22,464
Walling & superstructure
Masonry, lintels, ring beam and any suspended floor.
22%$17,741$32,947
Roofing
Trusses or rafters, covering, ceilings, fascia and rainwater goods.
14%$11,290$20,966
Internal finishes
Plaster, screed, floor and wall tiling, ceilings and painting.
18%$14,515$26,957
Joinery & fittings
Doors, windows, cupboards, worktops and ironmongery.
9%$7,258$13,478
Services (plumbing & electrical)
Wiring, distribution board, fittings, water reticulation, sanitaryware and drainage.
14%$11,290$20,966
External works & preliminaries
Site setup, supervision, paths, boundary works and connections.
8%$6,451$11,981

Get the real number for your own plans

A benchmark tells you the ballpark. Upload your dimensioned drawings and get an itemised, source-cited bill of quantities priced in YER (), measured to the POMI standard Yemen professionals use.

Price my Yemen project
Advertisement

Building 4-bedroom houses in Yemen — frequently asked

How much does it cost to build a 4-bedroom house in Yemen?

+

Building a 4-bedroom house in Yemen typically costs $80,640 to $149,760 in construction cost — roughly $336–$624 per square metre over 240 m² of floor area. That excludes land, professional fees and statutory charges. At a basic specification the same building lands nearer $58,061–$107,827; at a premium specification, $116,928–$217,152.

What is the cost per square metre in Yemen?

+

About $336–$624 per m² for this building type at a standard finish. Per-m² rates rise with storey height (frame, cores and cranage) and with specification, and fall on simple single-storey plans.

What is the biggest cost item?

+

Walling & superstructure — about 22% of construction cost, or $17,741–$32,947 on this build. Masonry, lintels, ring beam and any suspended floor.

Does this include land, fees and furniture?

+

No. These are construction costs only — materials, labour, plant and site preliminaries. Land, statutory approvals, professional fees, connections, landscaping and loose furniture are all additional, and together commonly add 15–30% on top.

How do I get an accurate figure for my own plans in Yemen?

+

Benchmarks give you the ballpark; a measured bill of quantities gives you the number. Upload your dimensioned floor plans to Enormous Buildings and get an itemised, source-cited BoQ in YER in the POMI format that Yemen quantity surveyors and lenders expect — free to preview.

Why do build costs vary so much between countries?

+

Three things dominate: labour cost, how much of the material basket is imported, and the code requirements the building must satisfy. Yemen sits at index 24 against the United States at 100, which is why the figures above differ from what you'd see quoted for the same building elsewhere.