Preliminaries in a Bhutan bill of quantities

In Bhutan, the preliminaries section of a Bill of Quantities (BoQ) is measured to IS 1200 — Method of Measurement of Building Works (India). It covers 7 principal groups of work — site establishment — hoarding, site office, storage, sanitation through to site clearance and making good on completion — and is headed in the bill as "BILL NO. 3 — PRELIMINARIES".

Preliminaries is one of the sections every Bill of Quantities (BoQ) in Bhutan is built from. This page sets out what belongs in it, the unit each item is measured in under IS 1200 — Method of Measurement of Building Works (India), the local conventions that change the quantities here, and a worked example for a 150 m² house — plus the errors in this section that actually cost money on site.

Advertisement

What this section covers

  • Site establishment — hoarding, site office, storage, sanitation
  • Temporary services: water, power and their connection charges
  • Contractor's supervision and site management for the contract period
  • Plant and scaffolding held on site rather than used by a single trade
  • Insurances, performance bond and statutory levies
  • Setting out, survey and as-built records
  • Site clearance and making good on completion

How each item is measured

ItemUnitMeasurement rule
Site establishmentitemPriced as a lump sum for the whole contract, not measured against any quantity of work.
Supervision and managementweekTime-related: measured against the contract period, so a longer programme costs more even if the work does not change.
Scaffoldingitem / m²Either a lump sum for the building or measured on the elevation area it serves.
Insurances and bondsitemA percentage of contract value, entered as a lump sum.
Temporary servicesitemConnection charges plus a running allowance for the programme duration.
Advertisement

Local conventions in Bhutan

  • With no municipal sewer, temporary sanitation means hired units serviced on a schedule — a recurring cost across the whole programme, not a one-off.
  • A subtropical climate affects the wet-weather allowance: programme time lost to rain is a preliminaries cost, not a trade cost, and it is the single most common under-estimate in this section.
Advertisement

What goes wrong in this section

  • Preliminaries typically run 8–15% of contract value. A bill that shows 3% is not cheap — it means the cost has been buried in the trade rates where you cannot see or control it.
  • Time-related items scale with the programme. Every week of delay re-prices this section, which is why extension-of-time claims land here first.
  • Omitting preliminaries entirely and 'spreading it in the rates' makes variations impossible to price fairly later.

Get every section measured, not just this one

Upload your dimensioned drawings and get a complete bill of quantities (boq) in the IS 1200 format, priced in BTN (Nu.), with every rate source-cited.

Generate my Bhutan BoQ

Preliminaries — frequently asked

What goes into the preliminaries section of a bill of quantities in Bhutan?

+

Site establishment — hoarding, site office, storage, sanitation; Temporary services: water, power and their connection charges; Contractor's supervision and site management for the contract period; Plant and scaffolding held on site rather than used by a single trade; and 3 further groups of work. Under IS 1200 each is described, measured in its own unit, and priced separately so the total is auditable line by line.

What units is preliminaries measured in?

+

Site establishment in item, Supervision and management in week, Scaffolding in item / m², Insurances and bonds in item. Getting the unit right matters more than getting the quantity precisely right — a contractor can adjust a quantity, but cannot price an item measured in the wrong unit at all.

How is preliminaries different in Bhutan from elsewhere?

+

With no municipal sewer, temporary sanitation means hired units serviced on a schedule — a recurring cost across the whole programme, not a one-off.

What is the most common costly mistake in this section?

+

Preliminaries typically run 8–15% of contract value. A bill that shows 3% is not cheap — it means the cost has been buried in the trade rates where you cannot see or control it.

How do I get this section measured for my own project?

+

Upload your dimensioned drawings to Enormous Buildings. The bill is produced in the IS 1200 format, grouped by section with preliminaries priced in BTN (Nu.), and every unit rate carries a source so a Bhutan quantity surveyor can check it.

The other sections of a Bhutan bill