Preliminaries in a the Philippines bill of quantities

In the Philippines, the preliminaries section of a Bill of Quantities / Program of Works is measured to DPWH-style estimate (MasterFormat-influenced, Philippines). It covers 7 principal groups of work — site establishment — hoarding, site office, storage, sanitation through to site clearance and making good on completion — and is headed in the bill as "PART 3 — PRELIMINARIES".

Preliminaries is one of the sections every Bill of Quantities / Program of Works in the Philippines is built from. This page sets out what belongs in it, the unit each item is measured in under DPWH-style estimate (MasterFormat-influenced, Philippines), the local conventions that change the quantities here, and a worked example for a 150 m² house — plus the errors in this section that actually cost money on site.

Advertisement

What this section covers

  • Site establishment — hoarding, site office, storage, sanitation
  • Temporary services: water, power and their connection charges
  • Contractor's supervision and site management for the contract period
  • Plant and scaffolding held on site rather than used by a single trade
  • Insurances, performance bond and statutory levies
  • Setting out, survey and as-built records
  • Site clearance and making good on completion

How each item is measured

ItemUnitMeasurement rule
Site establishmentitemPriced as a lump sum for the whole contract, not measured against any quantity of work.
Supervision and managementweekTime-related: measured against the contract period, so a longer programme costs more even if the work does not change.
Scaffoldingitem / m²Either a lump sum for the building or measured on the elevation area it serves.
Insurances and bondsitemA percentage of contract value, entered as a lump sum.
Temporary servicesitemConnection charges plus a running allowance for the programme duration.
Advertisement

Local conventions in Philippines

  • With no municipal sewer, temporary sanitation means hired units serviced on a schedule — a recurring cost across the whole programme, not a one-off.
  • A subtropical climate affects the wet-weather allowance: programme time lost to rain is a preliminaries cost, not a trade cost, and it is the single most common under-estimate in this section.
Advertisement

What goes wrong in this section

  • Preliminaries typically run 8–15% of contract value. A bill that shows 3% is not cheap — it means the cost has been buried in the trade rates where you cannot see or control it.
  • Time-related items scale with the programme. Every week of delay re-prices this section, which is why extension-of-time claims land here first.
  • Omitting preliminaries entirely and 'spreading it in the rates' makes variations impossible to price fairly later.

Get every section measured, not just this one

Upload your dimensioned drawings and get a complete bill of quantities / program of works in the DPWH-style estimate format, priced in PHP (), with every rate source-cited.

Generate my Philippines BoQ

Preliminaries — frequently asked

What goes into the preliminaries section of a bill of quantities in the Philippines?

+

Site establishment — hoarding, site office, storage, sanitation; Temporary services: water, power and their connection charges; Contractor's supervision and site management for the contract period; Plant and scaffolding held on site rather than used by a single trade; and 3 further groups of work. Under DPWH-style estimate each is described, measured in its own unit, and priced separately so the total is auditable line by line.

What units is preliminaries measured in?

+

Site establishment in item, Supervision and management in week, Scaffolding in item / m², Insurances and bonds in item. Getting the unit right matters more than getting the quantity precisely right — a contractor can adjust a quantity, but cannot price an item measured in the wrong unit at all.

How is preliminaries different in the Philippines from elsewhere?

+

With no municipal sewer, temporary sanitation means hired units serviced on a schedule — a recurring cost across the whole programme, not a one-off.

What is the most common costly mistake in this section?

+

Preliminaries typically run 8–15% of contract value. A bill that shows 3% is not cheap — it means the cost has been buried in the trade rates where you cannot see or control it.

How do I get this section measured for my own project?

+

Upload your dimensioned drawings to Enormous Buildings. The bill is produced in the DPWH-style estimate format, grouped by section with preliminaries priced in PHP (₱), and every unit rate carries a source so a the Philippines quantity surveyor can check it.