🇲🇱 Mali · DQE / DPGF · Work section

Substructure & foundations in a Mali bill of quantities

In Mali, the substructure section of a Bill of Quantities (Devis Quantitatif Estimatif) (Devis Quantitatif Estimatif (DQE) / DPGF) is measured to DQE / DPGF (French practice). It covers 7 principal groups of work — site clearance and removal of topsoil through to ground floor slab and any thickenings — and is headed in the bill as "LOT 3 — SUBSTRUCTURE & FOUNDATIONS".

Substructure & foundations is one of the sections every Bill of Quantities (Devis Quantitatif Estimatif) (Devis Quantitatif Estimatif (DQE) / DPGF) in Mali is built from. This page sets out what belongs in it, the unit each item is measured in under DQE / DPGF (French practice), the local conventions that change the quantities here, and a worked example for a 150 m² house — plus the errors in this section that actually cost money on site.

Advertisement

What this section covers

  • Site clearance and removal of topsoil
  • Excavation to reduce levels and to foundation trenches
  • Earthwork support and keeping excavations free of water
  • Disposal of excavated material, on site or off
  • Mass or reinforced concrete footings
  • Hardcore filling, blinding and damp-proof membrane
  • Ground floor slab and any thickenings

How each item is measured

ItemUnitMeasurement rule
ExcavationMeasured net from existing ground level to the underside of the concrete. Working space is a separate item, not an addition to the volume.
DisposalBulk excavated volume, with an allowance for bulking — spoil occupies more once dug than it did in the ground.
Concrete in footingsMeasured net; no deduction for reinforcement or for voids under about 0.05 m³.
Hardcore fillingm³ or m²Measured to the compacted thickness. Loose delivered volume is materially greater.
Damp-proof membraneNet area covered; laps and turn-ups are deemed included in the rate.
Ground floor slabm³ or m²Measured on the net area, stating the thickness.
Advertisement

Local conventions in Mali

  • Foundations here are conventionally strip type, taken 0.6 m deep and 400 mm wide.
  • Footing concrete is normally a 1:2:4 mix, with 50 mm blinding beneath and 150 mm of hardcore under the slab.
  • A damp-proof course and membrane are standard practice and must be measured — leaving them out is the most expensive omission in this section.

Worked example — 150 m² house in Mali

Quantities for this section on a representative single-storey house, computed from Mali construction conventions. Rates are deliberately not shown: they move constantly and are priced against your own drawings.

DescriptionQtyUnit
Trench excavation
50 m perimeter × 0.4 m wide × 0.6 m deep
12
Mass concrete footings
225 mm thick strip footing, mix 1:2:4
4.5
Hardcore filling
150 mm bed under the ground slab
22.5
Blinding concrete
50 mm blinding over hardcore
7.5
Ground floor slab concrete
100 mm slab over 150 m²
15
Damp-proof course / membrane
Slab area plus 10% laps
165
Advertisement

What goes wrong in this section

  • Substructure is the section most often priced from the drawing rather than from the ground. A trial pit that finds soft material below founding level re-prices the whole section.
  • Trench depth and concrete thickness are different numbers. Measuring concrete to the full trench depth over-orders by a third or more.
  • Disposal is routinely forgotten. On a constrained urban site, carting spoil away can cost more than digging it.

Get every section measured, not just this one

Upload your dimensioned drawings and get a complete bill of quantities (devis quantitatif estimatif) in the DQE / DPGF format, priced in XOF (CFA), with every rate source-cited.

Generate my Mali BoQ

Substructure & foundations — frequently asked

What goes into the substructure section of a bill of quantities in Mali?

+

Site clearance and removal of topsoil; Excavation to reduce levels and to foundation trenches; Earthwork support and keeping excavations free of water; Disposal of excavated material, on site or off; and 3 further groups of work. Under DQE / DPGF each is described, measured in its own unit, and priced separately so the total is auditable line by line.

What units is substructure & foundations measured in?

+

Excavation in m³, Disposal in m³, Concrete in footings in m³, Hardcore filling in m³ or m². Getting the unit right matters more than getting the quantity precisely right — a contractor can adjust a quantity, but cannot price an item measured in the wrong unit at all.

How is substructure & foundations different in Mali from elsewhere?

+

Foundations here are conventionally strip type, taken 0.6 m deep and 400 mm wide.

What is the most common costly mistake in this section?

+

Substructure is the section most often priced from the drawing rather than from the ground. A trial pit that finds soft material below founding level re-prices the whole section.

How do I get this section measured for my own project?

+

Upload your dimensioned drawings to Enormous Buildings. The bill is produced in the DQE / DPGF format, grouped by section with substructure & foundations priced in XOF (CFA), and every unit rate carries a source so a Mali quantity surveyor can check it.