Bill of Quantities Format: Templates, Examples & Standards Explained

Confused about BoQ formats? This guide breaks down NRM2, SMM7, and CSI MasterFormat with real examples and template structures you can use immediately.

DG

The Great Dak

Enormous Buildings

Updated Jul 14, 2026

Understanding Bill of Quantities Formats

A bill of quantities format defines how items are organized, described, and presented in a BoQ document. The format you choose affects how contractors interpret your BoQ and how accurately they can price it.

The Standard BoQ Structure

Regardless of the measurement standard used, most BoQs follow this general structure:

1. Cover Page

  • Project name and location
  • Client/owner name
  • Architect/designer name
  • Date of BoQ preparation
  • BoQ reference number

2. Preliminaries Section

General project costs not tied to specific quantities:

  • Site establishment and security
  • Temporary works and facilities
  • Insurance and bonds
  • Health and safety requirements
  • Quality control and testing
  • Contingencies

3. Measured Works (by Trade)

The core of the BoQ, organized by construction trade:

4. Summary

  • Trade-by-trade subtotals
  • Grand total
  • Notes and exclusions

BoQ Format Example: Residential Project

Here's a simplified example of a BoQ format for a residential floor plan:


PROJECT: Smith Residence — Ground Floor

TRADE: FLOOR FINISHES

Item No.DescriptionUnitQtyRateTotal
F.01Ceramic floor tiling, 600×600mm polished porcelain, cement mortar bed, to living room32.50
F.02Ceramic floor tiling, 600×600mm polished porcelain, cement mortar bed, to kitchen18.20
F.03Ceramic floor tiling, 600×600mm polished porcelain, cement mortar bed, to dining16.80
F.04Ceramic floor tiling, 300×300mm matte, to bathroom8.40
F.05Ceramic skirting, 100mm high, matching floor tilesm42.60
F.06Waterproof membrane to bathroom floor8.40

TRADE: WALL FINISHES

Item No.DescriptionUnitQtyRateTotal
W.01Internal wall plastering, 15mm thick, cement:sand 1:4156.40
W.02External wall plastering, 20mm thick, waterproof68.20
W.03Emulsion paint, 2 coats, to internal walls156.40
W.04Weatherproof paint, 2 coats, to external walls68.20

TRADE: DOORS AND WINDOWS

Item No.DescriptionUnitQtyRateTotal
D.01Hardwood door, 900×2100mm, including frame and ironmongerynos4
D.02Bathroom door, 800×2100mm, PVC, including framenos2
W.01Aluminium sliding window, 1500×1200mm, clear glassnos6
W.02Aluminium sliding window, 900×1200mm, clear glassnos3

Major Measurement Standards Compared

NRM2 (New Rules of Measurement 2)

Used in: UK, Commonwealth countries, international projects

Structure:

  • Group: Major trade category (e.g., "Substructure")
  • Sub-group: Sub-category (e.g., "Excavation")
  • Work section: Specific work type (e.g., "Excavation for foundations")

Key features:

  • Detailed rules for measurement
  • Clear classification system
  • Widely accepted in international tenders
  • Updated and maintained by RICS

SMM7 (Standard Method of Measurement, 7th Edition)

Used in: UK, Commonwealth countries (legacy)

Structure:

  • Similar to NRM2 but older format
  • 27 work sections covering all trades
  • Still widely used despite NRM2 being newer

Key features:

  • Well-established and understood
  • Extensive guidance notes
  • Familiar to older practitioners
  • Being gradually replaced by NRM2

CSI MasterFormat

Used in: USA, Canada

Structure:

  • Divisions (01–49) covering all construction work
  • Sub-divisions for detailed breakdown
  • Standardized numbering system

Key divisions:

  • Division 03: Concrete
  • Division 04: Masonry
  • Division 05: Metals
  • Division 06: Wood, Plastics, Composites
  • Division 07: Thermal and Moisture Protection
  • Division 08: Openings (Doors/Windows)
  • Division 09: Finishes

POMI (Principles of Measurement International)

Used in: International projects (World Bank, aid projects)

Structure:

  • Simplified format for international use
  • Less prescriptive than NRM2 or SMM7
  • Focuses on consistency across borders

How to Choose the Right BoQ Format

SituationRecommended Format
UK projectNRM2
International tenderNRM2 or POMI
US/Canada projectCSI MasterFormat
Legacy UK projectSMM7 (if specified)
Private project (no standard required)Any consistent format
AI-generated BoQEnormous Buildings (NRM2-style)

BoQ Template Structure

Use this template structure for your next BoQ:

[PROJECT NAME]
Bill of Quantities
[Date]

SECTION A: PRELIMINARIES
A.1  Site establishment
A.2  Temporary facilities
A.3  Insurance
A.4  Contingencies

SECTION B: SUBSTRUCTURE
B.1  Excavation
B.2  Foundations
B.3  Concrete works
B.4  Backfill

SECTION C: SUPERSTRUCTURE
C.1  Walls (external)
C.2  Walls (internal)
C.3  Columns and beams
C.4  Floor structure

SECTION D: ROOFING
D.1  Roof structure
D.2  Roof covering
D.3  Insulation
D.4  Gutters and downpipes

SECTION E: DOORS AND WINDOWS
E.1  Doors
E.2  Windows
E.3  Ironmongery

SECTION F: FLOOR FINISHES
F.1  Screeds
F.2  Tiling
F.3  Timber flooring
F.4  Skirting

SECTION G: WALL FINISHES
G.1  Plastering
G.2  Painting
G.3  Wall tiling

SECTION H: CEILING FINISHES
H.1  Plaster ceilings
H.2  Suspended ceilings
H.3  Painting

SECTION I: ELECTRICAL
I.1  Wiring
I.2  Fittings
I.3  Distribution

SECTION J: PLUMBING
J.1  Water supply
J.2  Sanitary fixtures
J.3  Drainage

SECTION K: EXTERNAL WORKS
K.1  Paving
K.2  Landscaping
K.3  Fencing

SUMMARY
[Trade subtotals and grand total]

Generating a Formatted BoQ Automatically

Manually creating a formatted BoQ from scratch is tedious. Enormous Buildings generates a properly formatted, trade-categorized bill of quantities automatically from your floor plan:

  1. Upload your floor plan
  2. AI identifies all building elements
  3. Quantities are calculated and categorized by trade
  4. Export in your preferred format (Excel, CSV, PDF)

The output follows industry-standard formatting with item numbers, descriptions, units, and quantities—all ready for pricing.

Generate a formatted BoQ →

Frequently Asked Questions

What is the standard format for a bill of quantities?

The standard format for a bill of quantities depends on your region: NRM2 (New Rules of Measurement) in the UK and internationally, SMM7 in legacy UK projects, and CSI MasterFormat in the USA and Canada. All formats organize items by trade category with columns for description, unit, quantity, rate, and total.

Where can I get a BoQ template?

You can create a BoQ template using the structure outlined in this guide, or generate one automatically using Enormous Buildings. The AI tool produces a professionally formatted BoQ with trade categorization, item descriptions, units, and quantities from your floor plan.

What is the difference between NRM2 and SMM7?

NRM2 (New Rules of Measurement 2) is the newer RICS standard replacing SMM7 (Standard Method of Measurement, 7th Edition). NRM2 provides more detailed measurement rules and is the current recommended standard, while SMM7 is still used in legacy projects but is being phased out.

How do I format a BoQ in Excel?

Format a BoQ in Excel with columns for item number, description, unit, quantity, rate, and total. Organize items by trade category with subheadings. Use formulas to calculate totals (quantity × rate). Enormous Buildings exports directly to Excel with all formatting and trade categorization included.